Progress of CCTNS in Chronological order |
|
SL No. |
Date |
Meeting details |
|
1 |
07.05.08 |
CCTNS was conceived on 7th May, 2008 as per MHA's letter No. IV.24021/2/08-PM-I dated 7th May 2008. |
|
2 |
31.12.08 |
Submission of CCTNS State plan by States/Uts |
|
3 |
09.03.09 |
Visit of Director NCRB to Chhatisgarh ( Raipur ) on 09.03.09 to assess the progress of CIPA/CCTNS. |
|
4 |
18.03.09 |
Empowered Committee meeting on 18.03.09 under the chairmanship of Additional Secretary (CS), MHA. NISG has been identified as CPMC. NCRB will be responsible for development and management of CAS. CIPA to continue till CCTNS is developed. Target dates for different activities fixed. |
|
5 |
19/20.03.09 |
Visit of Director NCRB to Andhra Pradesh on 19/20.03.09 to assess the progress of CIPA/CCTNS. |
|
6 |
25.03.09 |
Visit of Director NCRB to Tamilnadu (Chennai) on 25.03.09 to assess the progress of CIPA/CCTNS. |
|
7 |
09.04.09 |
Visit of Jt. Director (CCTNS) to Jharkhand on 09.04.09 to assist the state authorities in preparing the CCTNS state plan. |
|
8 |
15.04.09 |
Meeting of Empowered Committee on 15.04.09 under the chairmanship of Additional Secretary (CS), MHA to discuss various provisions in the EOI. Infrastructure to be established at NCRB for development of CAS. |
|
9 |
20.04.09 |
Meeting of Director NCRB with NISG on 20.04.09 on Expression of Interest (EOI)/ CAS. |
|
10 |
24.04.09 |
Meeting of Director, NCRB with Sh. Sunil Kumar, Exe Dir. Railway Board on 24.04.09 on EOI/Networking and other related issues. |
|
11 |
27.04.09 |
Empowered Committee Meeting held on 27.04.09 under the chairmanship of Additional Secretary (CS), MHA. Decision taker on NCRB to have the strategic control and ownership of the application and NIC to depute some technical experts to work with NCRB team. |
|
12 |
28.04.09 |
Draft Expression of Interest (EOI) prepared by NISG on 28.04.09 |
|
13 |
29.04.09 |
Presentation on Security solution by Agape e-Business Ltd. on 29.04.09 given to Director NCRB and other members of CCTNS Core Group. |
|
14 |
30.04.09 |
Meeting in NCRB with Shri Sunil Kumar, Exe. Dir., Railway Board and Ms. Rita Gupta, NISG on 30.04.09 under the chairmanship of Director NCRB |
|
15 |
01.05.09 |
Draft Expression of Interest (EOI) sent to members of Empowered Committee by mail and by dak on 01.05.09 |
|
16 |
04.05.09 |
Proposal for creation of 48 posts in NCRB and for sanction of Rs. 2 crore towards pre-investment expenditure to NCRB sent to MHA on 04.05.09 |
|
17 |
05.05.09 |
Meeting with JS (CS) MHA on 05.05.09 to discuss points for meeting with HS. |
|
18 |
06.05.09 |
Meeting with HS on 06.05.09 about Rs. 172/- crore to be spent on Capacity Building under CCTNS project. |
|
19 |
12.05.09 |
Meeting with Sh. Sunil Kumar regarding development of CCTNS software was held on 12.05.2009 |
|
20 |
13.05.09 |
Meeting with Sh. Sunil Kumar regarding development of CCTNS roadmap, role of NCRB, issues regarding ownership,/ operation responsibility/ accountability etc. at various levels was held on 13.05.2009 under the chairmanship of Director NCRB |
|
21 |
19.05.09 |
A meeting to discuss various modules to be included in CAS and approval of 48 posts created under CCTNS project was held on 19.05.2009 under the chairmanship of Additional Secretary (CS), MHA. |
|
22 |
25.05.09 |
Meeting of Nodal Officers held at NCRB on 25.05.09 under the chairpersonship of Director NCRB. |
|
23 |
01.06.09 |
Meeting with MD and other officers of CRIS were held on 01.06.2009 to discuss the centralized database management system. |
|
24 |
05.06.09 |
Meeting with Sh. Sunil Kumar, Exe. Director, Railway Board on 05.06.09 to discuss about the prototype of CAS based on Integrated Investigation Firm (IIF). |
|
25 |
08.06.09 |
Empowered Committee Meeting held on 08.06.09 under the chairpersonship of Special Secretary (CS), MHA to discuss state plans, creation of posts in NCRB and induction of experts into expert groups/committee. |
|
26 |
09.06.09 |
Meeting with Sh Sunil Kumar, Exe. Director, Railway Board and NSIG held on 09.06.09 to assess the capabilities of developers of CCIS application software. |
|
27 |
17.06.09 |
Empowered Committee Meeting on 17.06.2009 under the chairmanship of Additional Secretary (CS), MHA to finalize EOI. |
|
28 |
19.06.09 |
CCTNS Project was approved by Cabinet Committee on Economic Affairs (CCEA) on 19.06. 09. |
|
29 |
09.07.09 |
Empowered Committee Meeting on 09.07.09 under the chairmanship of Special Secretary (CS), MHA to finalize the guidelines for implementation and capacity building aspects, model RFP for selection of SI and FRS of phase -1. |
|
30 |
13.07.09 |
Discussion with Sh. Sunil Kumar Exe. Director, Railway Board on 13.07.09 on various points about signing of MoU with States. |
|
31 |
22.07.09 |
Expression of Interest (EOI) approved by the Empowered Committee on 22.07.09 and sent to DAVP for publication. |
|
32 |
27.07.09 |
Discussions on Networking of CCTNS held on 27.07.09 under the chairmanship of Joint Secretary (CS), MHA. |
|
33 |
28.07.09 |
Advertisement on CCTNS EOI published in Times of India (English daily) and Hindustan (Hindi daily) on 28.07.2009 |
|
34 |
20/24.08.09 |
Nodal Officers meeting on 20th and 24th Aug. 2009 under the chairmanship of DG, NCRB / JS (CS) |
|
35 |
21.07.09 |
Implementation Guidelines, Capacity Building Guidelines, Model SI RFP draft, FRS draft and SPMC guidelines sent to all States / UTs vide JS (CS), MHA Do letters dated 15th and 21st July, 2009. |
|
36 |
29.08.09 |
Draft MOU etc. sent to all States / UTs vide AS (CS), MHA DO letter dated 29 August 2009. |
|
37 |
11.09.09 |
Meeting with MTNL and BSNLheld on 11.09.09 to discuss about connectivity requirements of CCTNS project under the chairmanship of DG, NCRB. |
|
38 |
08.09.09 |
Pre-EOI bid conference held at NCRB on 08.09.2009 under the chairmanship of JD (CCTNS), NCRB. |
|
39 |
11.09.09 |
Meeting of the Empowered Committee for CCTNS held on 11.09.09 under the chairmanship of Additional Secretary (CS), MHA to discuss responses for EOI for development of CAS. |
|
40 |
16.09.09 |
Presentation on CCTNS Project implementation was given by DG, NCRB to the participants of DGP/IGP conference held on 16.09.09 |
|
41 |
19.09.09 |
Meeting of the Central Technical Team held on 19.09.09 under the chairmanship of DG, NCRB to discuss central architecture and customization in CCTNS project. |
|
42 |
22.09.09 |
Empowered Committee Meeting held on 22.9.09 under CCTNS project under the chairmanship of Additional Secretary (CS), MHA to discuss comments of DIT, NIC, CTT on RFP. It was decided that RFP be shared with all the short listed bidders for their feedback for strengthening the RFP before finalization. |
|
43 |
30.09.09 |
MoU signed between MHA and 22 states/UTs |
|
44 |
14.10.09 |
First Regional workshop of CCTNS nodal officers from seven states i.e. Bihar, Chattisgarh, Jharkhand, Madhya Pradesh, Orissa, Uttarakhand and Uttar Pradesh was held on 14.10.09 at Lucknow to assess the progress of CCTNS in the states. |
|
45 |
15.10.09 |
Pre-RFP meeting with Software Development Vendors short listed after processing their EOI, held in the Conference Room of NCRB on 15.10.2009 |
|
46 |
23.10.09 |
Empowered Committee meeting held on 23.10.2009 in MHA under Chairmanship of Union Home Secretary to consider and approve the RFP for the selection of Software Development Agency for the development of CCTNS Core Application Software and decision regarding the list of eligible bidders for issuing the RFP. |
|
47 |
30.10.09 |
Second Regional workshop of CCTNS Nodal officers of Chandigarh , Delhi , Haryana, Himachal Pradesh , Jammu and Kashmir , Jharkhand, Punjab and Rajasthan chaired by DG, NCRB was held at Chandigarh PHQ on 30.10.2009. |
|
48 |
03.11.09 |
Second Pre-RFP meeting with software development vendors short listed after processing EOI was held in the conference room of NCRB on 03.11.2009 under the chairmanship of JS (CS), MHA. |
|
49 |
18.11.09 |
Third Regional Workshop of CCTNS Nodal officers of southern States/UTs was held at Bangaluru on the 18.11.2009 under the chairmanship of DG, NCRB in which DGP Karnataka and nodal officer from the states of Andhra Pradesh, Tamil Nadu, Karnataka, Kerala and UTs of A&N island, Lakshadweep and Pondicherry attended. |
|
50 |
27.11.09 |
Empowered Committee Meeting held on 27.11.2009 under the chairmanship of Addl. Secretary (CS) at MHA to discuss Vol. III (Contractual and Legal specifications) of RFP for the selection of SDA and strengthening of NCRB. |
|
51 |
08.12.09 |
Bids (Technical and Financial) have been submitted by the eligible vendors on 8th December 2009, the last date for submission of bids. The Technical bids where opened in the presence of Joint Director (A&T), NCRB. |
|
52 |
18.12.09 |
Fourth Regional workshop of CCTNS Nodal Officers of Gujarat, Goa, Maharastra, Daman & Diu and Dadra & Nagar Haveli was held at Gandhinagar on 18.12.2009 under the chairmanship of Director, SCRB, and Gujarat . |
|
53 |
29.12.09 |
a) Empowered Committee meeting held on 29.12.2009 under the chairmanship of Special Secreatary (CS), MHA regarding Constitution of Technical Evaluation Committee (TEC) for development of core application software for CCTNS. |
|
|
|
b) Inclusion of Police academies for training of State level Police officers on CCTNS. |
|
54 |
07.01.10 |
Hindi version of Basic Training Modules( Circulated earlier by NCRB in english) prepared by UP Police Computer Centre has been uploaded on NCRB website on 7.1.2010 |
|
55 |
28.01.10 |
The chairman of Technical Evaluation Committee (TEC) was decided finally on 28th Jan'10. Sh. Krishna Prasad, IG, Police Computer Services (PCS) and Andhra Pradesh has been nominated as the chairman. |
|
56 |
28.01.10 |
A review meeting was taken by Shri Ajay Maken, Hon'ble Minister for State (Home) on 28th January 2010 at MHA, North Block to review the progress of CCTNS. |
|
57 |
02/03.02.10 |
The first Technical Evaluation Committee (TEC) meeting was held on 2nd & 3rd Feb'10 for evaluating proposed technical solutions of CAS by the 7 shortlisted bidders |
|
58 |
04.02.10 |
First instalment of CCTNS funds for the remaining four states i.e. Andhra Pradesh, Karnataka, Gujarat and Nagaland have been released by MHA |
|
59 |
05.02.10 |
Template for preparing Project Implementation and Monitoring (PIM) report has been released to States/UTs. |
|
|
State Project Management Committee(S-PMC) has been appointed in Gujarat, Kerala, Maharashtra, Punjab, Tamil Nadu and Lakshadweep . |
|
|
|
The selection process of S-PMC has comenced in Arunachal Pradesh, Chhatisgarh, Goa, Himachal Pradesh, Jammu & Kashmir, Madhya Pradesh, Rajasthan, Uttar Pradesh, Andaman & Nicobar Island , Chandigarh and Pondicherry . |
|
|
60 |
08.02.10 |
The clarifications were sought from bidder on 8th Feb'10. |
|
61 |
11.02.10 |
Clarification received on 11th Feb'10 |
|
62 |
16.02.10 |
A meeting of the Technical Evaluation Committee to scrutinize the technical bids of the vendors for design, development and maintenance of CAS of CCTNS was held in NCRB on 16.02.2010. |
|
63 |
23.02.10 |
Technical Evaluation Committee Meeting at NCRB to evaluate the technical bids submitted by the vendors. |
|
64 |
24.02.10 |
Technical Evaluation Sub Committee Meeting at NCRB & DIT |
|
65 |
26.02.10 |
Technical Evaluation Committee (TEC) meeting held 26.02.10 |
|
66 |
04.03.10 |
Technical Evaluation Sub Committee meeting at NCRB & DIT |
|
67 |
17/18.03.10 |
Technical Evaluation Committee Meeting at NCRB to evaluate the technical bids submitted by the vendors. |
|
68 |
18.03.10 |
Emergency Tender Evaluation Committee Meeting at NCRB |
|
69 |
23.03.10 |
Technical Evaluation Committee Meeting at NCRB to evaluate the technical bids submitted by the vendors. |
|
70 |
29.03.10 |
Technical Evaluation Committee Meeting at NCRB. Undertaking has been called for from bidders. |
|
71 |
30.03.10 |
Technical Evaluation Committee has submitted its report to the Tender Evaluation Committee on 30.03.10 |
|
72 |
01.04.10 |
Financial bids of short listed Software Vendors were opened in the Tender Evaluation Committee Meeting for selecting a Software Vendor for designing and development of CAS (CCTNS) |
|
73 |
07.04.10 |
Tender Evaluation Committee meeting held at NCRB for recommending Software Development Agency for design, development and maintenance of Core Application Software (CAS) of CCTNS |
|
74 |
07.04.10 |
Final Report of Tender Evaluation Committee prepared under the chairmanship of DG, NCRB submitted to MHA. |
|
75 |
09.04.10 |
a) Union Home Secretary Visited NCRB to discuss the CCTNS Project & other issues concerning NCRB. |
|
|
|
b) Empowered Committee meeting held under the chairmanship of Special Secretary (CS) to discuss selection of SDA. |
|
76 |
12.04.10 |
Meeting convened by Union Home Secretary in his chamber to discuss NCRB's proposals. |
|
77 |
19.04.10 |
Empowered Committee meeting held under the chairmanship of Special Secretary (CS) on 19.04.2010 to discuss hiring of Technical Consultant/Expert. |
|
78 |
26.04.10 |
The competent authority approved the selection of M/s Wipro Ltd as Software Development Agency (SDA). |
|
79 |
28.04.10 |
Letter of Acceptance issued to M/s Wipro Ltd. for SDA for design, developments and management of CCTNS Core Application Software (CAS). |
|
80 |
04.05.10 |
CPeMT meeting held at MHA under the chairmanship of JS(CS). |
|
81 |
06.05.10 |
Meeting held with BSNL, DCPW, CRIS, and NCRB officers on the network proposal submitted by BSNL under the chairmanship of DG, NCRB. |
|
82 |
13.05.10 |
A meeting on networking and connectivity under the chairmanship of Hon'ble Union Home Secretary was held on 13.05.2010. We have brought to the focus the requirement of networking before HS. Three options of BSNL were placed before HS. In this meeting representatives from DIT, Railway board, CRIS, SBI participated. It was decided that option no: 2 will be adopted to begin with and will be upgraded to option no:1 in due course of time. |
|
83 |
25/26.05.10 |
Two days 21st Monitoring Committee meeting attended by the nodal officers of CCTNS and Directors SCRBx of all States/UTs. Important decision taken and difficulties resolved. |
|
84 |
04.06.10 |
Empowered committee meeting held under the chairpersonship of SS (CS), MHA to discuss the issues raised by M/s Wipro Ltd on some of the clauses in the contract document and finalize the contract. |
|
85 |
17.06.10 |
Review meeting by Union Home Secretary on all pending proposals regarding CCTNS in MHA. |
|
86 |
21.06.10 |
Contract for development of Core Application Software (CAS) for CCTNS signed with M/s Wipro Ltd on 21/06/2010. |
|
87 |
22/26.06.10 |
Advertisement printed in national newspapers for hiring of 15 IT professionals under CCTNS for NCRB |
|
88 |
28.06.10 |
Meeting of Nodal Officers held with M/s Wipro before visit of ten scheduled states by M/s Wipro for first hand understanding of ground conditions from PS level to state HQ level. |
|
89 |
16.07.10 |
Offer letters to IT Professionals hired on contractual basis were mailed and dispatched by speed post on 16.07.2010. |
|
90 |
21/22/23.07.10 |
Three day workshop for cutting edge level police officers of States/UTs under CCTNS was conducted wef 21-23.07.2010. The workshop aimed at getting domain experts from all States together in order to understand their needs/requirement from the new system and their concerns regarding the already implemented CIPA and CCIS system and also aimed at educating the cutting edge level officers about CCTNS. The format of FIR and other register including Crime register and other essential Police level register were discussed threadbare and finalized. |
|
91 |
09.08.10 |
Meeting with Accenture Ltd. under the chairmanship of DB, NCRB. Highlighting was on the policing in UK. |
|
92 |
19.08.10 |
Meeting of e-mission team for CCTNS with JS (CS). |
|
93 |
30.08.10 |
Meeting under the chairmanship of JD (CCTNS) for communication issued to Exe. Div. M/s. Pricewaterhousecoopers Pvt. Ltd., for setting up a CPMU for CCTNS. |
|
94 |
13.09.10 |
Empowered Committee meeting held under the chairmanship of AS (CS), MHA to assess the overall progress of CCTNS. |
|
95 |
29.09.10 |
|
|
96 |
01.10.10 |
One day workshop of Nodal Officers and SPMC representative was held at CRPF officer's institute. |
| 97. | 18/19.10.10 |
Workshop on Business Process Reengineering was held at NCRB and attended by the officers / police personnel of States / UTs. |
| 98. | 20/21.10.10 |
Workshop on Conference Room Pilot (CRP) was held at NCRB and attended by the officers / police personnel of States / UTs. |
| 99 | 15/16.11.10 |
Two days workshop on Conference Room Pilot (CRP) was held at NCRB on 15-16.11.2010. |
| 100. | 24.11.10 |
Meeting of Central Technical Team was held at DIT under the Chairmanship of Joint Secretary, DIT to discuss Network Connectivity issues. |
| 101. | 26.11.10 |
Empowered Committee Meeting was held under the Chairpersonship of Additional Secretary (CS) to assess the progress of CCTNS, discussion on various points pertaining to Fund Allocation and the process to be adopted for selection of SPMU. |
| 102. | 26.11.10 |
Pre-bid meeting of vendors for supply, installation, customization and commissioning IT solutions at NCRB, Jasola for CCTNS was held in the conference hall, NCRB. |
| 103. | 29.11.10 |
Meeting held in the office chamber of AS(CS) to discuss BSNL Network and Connectivity proposals for CCTNS Project. |
| 104. | 29.11.10 |
Meeting held in the office chamber of DG(NIC) for hosting of CCTNS National Data Centre at NIC's Data Centre located at Luxminagar. |
| 105. | 08.12.10 |
A review meeting to assess the progress of CCTNS was held in MHA under the chairpersonship of Union Home Secretary. |
| 106. | 10.12.10 |
Opening of Pre qualification bids was held in the presence of Joint Director (CCTNS) in the conference hall, NCRB. Vendors from 6 companies participated. |
| 107. |
18.01.11 |
A meeting was held to review and rationalize the Integrated Investigation Forms (IIFs) and attended by representatives of UP, Rajasthan, Haryana, Tamilnadu, Delhi and Puducherry beside NCRB, PWC and M/s Wipro. |
| 108. |
24.01.11 & 25.01.11 |
A meeting was held with various stakeholders to devise a module as per the Juvenile Justice Act and Rules to deal with cases related to Juveniles. |
| 109. | 17 & 18.02.11 |
CAS Core Group Meeting to review and provide recommendations on the deliverables of Software Development Agency (SDA) for design, development and maintenance of Core Application Software (CAS) of the CCTNS project was held under the chairpersonship of Additional DGP (Tech. Services), UP. |
| 110. | 24.02.11 |
Scope of work and deliverables of SDA as per its contractual obligations. |
| 111. | 09.03.11 |
Nodal officers meeting was held under the chairpersonship of DG, NCRB to assess the progress of CCTNS in the States/UTs. |
| 112. | 09.03.11 |
Meeting of CCTNS Nodal Officers of States/UTs was held on 09.03.2011 under the chairpersonship of DG, NCRB to review the progress of CCTNS project especially with regards to floating of SI-RFP. |
| 113. | 23.03.11 |
Empowered committee meeting was held on 23.03.2011 under the chairpersonship of Additional Secretary (CS), MHA to review the status of floating of SI-RFP by various states/UTs. The meeting also reviewed the progress made on floating of RFP for empanelment of State Project Management Unit (SPMU). |
| 114. | 04.04.11 |
Video Conferencing meeting was held under the chairpersonship of AS (CS) on 04.04.2011 at MHA to review the progress of CCTNS particularly with regards to floating of RFP for selection of SI and submission of utilization certificates. |
| 115. | 08.04.11 |
Meeting was held under the chairpersonship of Smt. B Bhamathi, AS (CS) to discuss the security aspects to be addressed in CCTNS project |
| 116. | 11.04.11 |
Meeting of central e-mission team was held under the chairpersonship of Sh. K. K. Pathak, JS(CS) to discuss the finalization of System Requirement Specification (SRS), timelines for software development, establishment of DC and DR site, Pilot testing, STQC testing etc. |
| 117. | 06.05.11 |
Meeting of Process Advisory Group was held under the Chairpersonship of DG, NCRB at Jasola office of NCRB. |
| 118. | 01.06.11 |
Workshop on pilot implementation on data digitization at NCRB |
| 119. | 06.06.11 |
Three days workshop for CAS implementation in Pilot states - Assam, Kerala and Uttar Pradesh from 06.06.2011 to 08.06.2011 |
| 120. | 15.06.11 |
Meeting with NIC for Data Centre on 15.06. 2011 and 29.06.2011. |
| 121. | 20.06.11 |
Meeting with DAR&PG for e-Office implementation |
| 122. | 20.06.11 |
CAS Core Group meeting under the chairmanship of Sh. Arun Kumar, IG and Nodal officers of Uttar Pradesh |
| 123. | 21.06.11 |
PAG meeting on 21.06.2011 and 29.06.2011 under the Chairmanship of DG, NCRB |
| 124. | 22.06.11 |
Workshop on SDA Contract with NISG |
| 125 | 24.06.11 |
Meeting with NATGRID for Security implementation for CCTNS |
| 126. | 13.07.11 |
CAS Steering Committee Meeting held at MHA under the chairmanship of Mr. K.K. Pathak, JS (CS) MHA. Agenda-1 was to discuss regarding the pre-bid qualifications criteria for evolutions of technical & financial bids of selection of SI in states/UT. Agenda-2 was to discuss regarding the finger prints issues etc. |
| 127. | 14.07.11 |
Workshop held on 14th July & 15th July 2011 on reviewing CAS User Interface Screen and Change Management in New Delhi. Participants states were Uttar Pradesh, Delhi, Madhya Pradesh, Rajasthan, Punjab, Haryana. |
| 128. | 21.07.11 |
Workshop held on reviewing CAS User Interface Screen Part-11 in New Delhi. Participants states were Uttar Pradesh, Delhi, Madhya Pradesh, Rajasthan, Punjab, Haryana, Andhra Pradesh |
| 129. | 28.07.11 |
(i)
Nodal Officers meeting was held under the chairmanship of Home Secretary
in MHA to assess the progress of CCTNS in the States/UTs.
(ii) Nodal officers meeting was held under
the chairmanship of DG, NCRB in Shaurya, CRPF Officers Institute to
assess the progress of CCTNS in the States/UTs. |
| 130. | 01.08.11 |
Central e-Mission Team (CeMT) meeting was held under the chairmanship of Mr. K. K. Pathak, JS(CS) MHA to discuss the SDA timelines for CAS development and Operational Project Status in the States/UTs. |
| 131. | 10.08.11 |
Steering Committee meeting was held under the chairmanship of Shri. R. K. Singh, Union Home Secretary to know the status of SDA progress report. |
| 132. | 19.08.11 |
CCTNS Regional workshop of southern States/UTs held at Kerala Police Academy, Thirussur under the chairpersonship of DG, NCRB to assess the progress of CCTNS project. The workshop was attended by the nodal officers of Andhra Pradesh, Kerala, Karnataka, Puducherry, Andaman & Nicobar Islands and Lakshwadeep. |
| 133. | 30.08.11 |
Empower committee meeting was held under the chairmanship of Additional Secretary(CS) in MHA |
| 134. | 01.09.11 |
Technical subcommittee meeting was held to discuss the specialised solutions under CCTNS by CPMU in NCRB |
| 135. | 02.09.11 |
Central e-Mission Team (CeMT) meeting was held under the chairpersonship of Mr. K. K. Pathak, JS(CS) at MHA to know the progress status of CCTNS project and the progress of NDC setup |
| 136. |
05.09.11 & 06.09.11 |
Training on CAS Lite to the representatives of pilot states of UP, and Assam |
| 137. | 15.09.2011 |
Training on CAS Lite to the representatives of pilot states of UP, and Assam |
| 138. | 16.09.11 |
All State/UT SPMU/SI/Nodal officers meeting was held to get acquainted with CCTNS Architecture and Application presented by SDA |
| 139. | 04.10.11 |
Second CCTNS Regional workshop of Central States/UTs held at Centre for Police Research, Pune, Maharashtra under the chairpersonship of DG, NCRB to assess the progress of CCTNS project. The workshop was attended by the nodal officers of Maharashtra, Gujrat, Goa, Dadra & Nagar Haveli and Daman & Diu. |
| 140. | 14.10.11 |
Third CCTNS Regional workshop of Bihar, Chhattisgarh, Uttar Pradesh, Uttarakhand, and Madhya Pradesh was held at Lucknow under the chairmanship of DG, NCRB to assess the progress of CCTNS project. The workshop was attended by the nodal officers of aforesaid states. |
| 141. | 14.10.2011 |
Central e-Mission Team (CeMT) meeting was held under the chairmanship of JS (CS) MHA. The following agenda points were discussed:
|
| 142. | 21.10.2011 |
Fourth CCTNS Regional workshop of Northern States/UT was held at Chandigarh under the chairmanship of DG,NCRB to assess the progress of CCTNS project. The workshop was attended by the nodal officers of Haryana, Himanchal Pradesh, Punjab, Chandigarh, Rajasthan, and Jammu & Kashmir. |
| 143. | 31.10.2011 |
Empowered committee meeting was held under the chairpersonship of AS(CS) to assess the progress of CCTNS selection of System Integrator (SI) in the States/UTs. |
| 144. | 02.11.2011 |
Meeting of CCTNS Nodal Officer of States/UTs held under the chairpersonship of the Union Home Secretary in the Conference Hall, North Block, MHA to assess the status of SIRFP, BSNL survey for connectivity and utilization of funds. |
| 145. | 03.11.2011 |
SDA Steering Committee meeting was held under the chairmanship of Joint Secretary(CS) at MHA. Participants were CPMU, NCRB & SDA. |
| 146. | 15.11.2011 |
A Meeting was held at MHA under the Chairmanship of Joint Secretary(CS) to discuss the Specialised Solutions and Infrastructure under the CCTNS project |
| 147. | 16.11.2011 |
PAG(Process Advisory Group) meeting was held at NCRB Conference Room under the Chairmanship of Smt. B. Bhamati AS(CS). |
| 148. | 21.11.2011 |
Central e-Mission Team (CeMT) meeting was held at MHA under the chairmanship of Mr. K.K. Pathak JS(CS) to know the progress status of CCTNS project, NDC setup and BSNL connectivity |
| 149. | 30.11.2011 |
A meeting under the chairmanship of Union Home Secretary was held in Conference Hall, North Block, MHA to discuss the issues regarding upgradation of POLNET. |
| 150. | 12.12.2011 |
Meeting on Network Solution
for CCTNS was held under the Chairmanship of JS(CS) at his chamber in
MHA. |
| 151. | 16.12.2011 |
Steering Committee meeting
was held under the Chairmanship of JS(CS) at his chamber in |
| 152. | 27.12.2011 |
Meeting on Network Solution
for CCTNS was held under the Chairmanship of Director(CS) at his chamber
in |
| 153. | 16.01.2012 |
CCTNS Nodal officers Meeting held under the Chairmanship of Joint Director(CCTNS), NCRB at Shaurya conference hall CRPF officers institute, New Delhi. The meeting was attended by the officers of BSNL, DIT, State DIT and SWAN operators of States/UTs besides CCTNS Nodal officer of States/UTs. The discussion points were: 1. Status of connectivity |
| 154. | 31.01.2012 |
Process Advisory Group(PAG) meeting was held under the Chairmanship of Smt. B. Bhamathi, Additional Secretary(CS) at MHA North Block New Delhi to know and discuss the status of overall progress of CCTNS project. |
| 155. | 02.02.2012 |
Empowered Committee meeting was held under the chairmanship of Additional Secretary (CS) at MHA to discuss the progress review of CCTNS, Network connectivity and the change request submitted by SDA. |
| 156. | 06.02.2012 |
An extensive User Acceptance Testing (UAT) of Core Application Software for CCTNS project was conducted for a period of 10 days from 6th Feb 2012 to 15th Feb 2012 at NCRB, R.K. Puram, New Delhi. The participant states were Delhi, Hariyana and Panjab. |
| 157. | 14.02.2012 |
Regional workshop on network connectivity was held at Kolkata on 14th Feb 2012 to discuss various issues related to CCTNS connectivity and speed-up the process for signing of SLA between BSNL and participating States, network committee formation and marking of CCTNS sites as per connectivity algorithm The nodal officers of West Bengal, Odisha, Jharkhand, Chhattisgarh and Sikkim along with representatives of DIT, BSNL, State DIT and State BSNL circle participated in the workshop. |
| 158. | 15.02.2012 |
Regional workshop on network connectivity was held at Guwahati, Assam on 15th Feb 2012 to discuss various issues related to CCTNS connectivity and speed-up the process for signing of SLA between BSNL and participating States, network committee formation and marking of CCTNS sites as per connectivity algorithm The nodal officers of Arunachal Pradesh, Assam, Meghalaya, Mizoram and Tripura along with representatives of DIT, BSNL, State DIT and State BSNL circle participated in the workshop. |
| 159. | 16.02.2012 |
Another User Acceptance Testing (UAT-Round 2) of Core Application
Software for CCTNS project was started for a period of 10 days from 16th
Feb 2012 to 25th Feb 2012 at NCRB, R.K. Puram New Delhi.
|
| 160. | 16.02.2012 |
Process Advisory Group(PAG) meeting was held under the |
|
161. |
27.02.2012 |
Regional
Workshop on CCTNS Connectivity was held at Rajasthan Police Academy
Jaipur, Rajasthan to discuss the various issues related to CCTNS
Connectivity and to speed up the process of signing the SLA
between BSNL& States, formation of network Committee and the marking of
CCTNS sites in coordination with SWAN/BSNL. |
| 162. | 03.03.2012 |
Regional Workshop on
CCTNS Connectivity was held at SCRB head Quarters Hyderabad, Andhra
Pradesh to discuss the various issues related to CCTNS Connectivity and
to speed up the process of signing the SLA between BSNL& States,
formation of network Committee and the marking of CCTNS sites in
Coordination with SWAN/BSNL. |
| 163. | 05.03.2012 |
User Acceptance Testinging (UAT round 3) of Core Application Software for CCTNS project had started at NCRB Office, R.K. Puram New Delhi from 5th March 2012 to 16th March 2012.
The participating states were West Bengal. Sikkim, Chandigarh and Maharashtra. NIA and NPA have also participated in the UAT round 3 for one day. |
| 164. | 13.03.2012 |
Review meeting was held under the chairmanship of Smt. B. Bhamathi, Additional Secretary (CS) at the North Block, MHA New Delhi. The agenda was to review and discuss the status of CAS application delivery. It was further discussed that SDA should plan meeting with NATGRID to discuss the issues on CAS application and finalize a plan for delivery of all the pending activities by SDA. |
| 165. | 14.03.2012 |
Process
Advisory Group (PAG) meeting was held under the Chairmanship of Smt. B.
Bhamathi, Additional Secretary (CS) at the Conference room NCRB Office,
and R. K. Puram New Delhi. |
| 166. | 27.03.2012 |
SDA Steering
Committee meeting was held under the Chairmanship of, Joint
Secretary (CS) at the North Block, MHA New Delhi. |
| 167. | 29.03.2012 |
CAS Core
Group meeting was held under the Chairmanship of Shri T. Krishna Prasad,
ADG (Provision & Logistics), Andhra Pradesh at the Conference Hall, NCRB
New Delhi for two days. 1.
Discussion and decision on mandatory fields in CAS (based on feedback
received during UAT Round –I, II & III and Intensive Field Testing) |
| 168. | 11-04-2012 |
Empowered
Committee (EC) meeting was held under the Chairmanship of, Joint
Secretary (CS) at the North Block, MHA New Delhi. |
| 169. | 18-04-2012 |
Process Advisory
Group (PAG) meeting was held under the Chairmanship of Smt. B. Bhamathi,
Additional Secretary (CS) at North Block, MHA New Delhi. |
| 170. | 27-04-2012 |
CAS Core Group
meeting was held under the Chairmanship of Shri T. Krishna Prasad, ADG
(Provision & Logistics), Andhra Pradesh at the Conference Hall, NCRB New
Delhi. 3. Review and discussion on
the revised project plan to be submitted by SDA.
|
| 171. | 30-04-2012 |
System
Integrator (SI) workshop for CCTNS project was held under the
chairmanship of Shri P.R.K Naidu, Joint Director (CCTNS) at Conference
Hall NCRB, New Delhi for States/UTs where the SI has been selected or
shortlisted. |
| 172. | 18-06-12 |
System Integrator's (SI's) workshop for CCTNS project was held under the chairpersonship of Shri Suresh Kumar, Joint Secretary (CS) at the conference hall, NCRB, New Delhi for States/UTs where the SIs have been selected or shortlisted.
The following points were the agenda for the workshop: Demonstration of Packaged
Installation of CAS Offline Overview of Configuration
Parameters within CAS Overview of CAS Customization
Framework Present Status of CAS
Application |
| 173. | 21-06-12 |
Empowered Committee (EC) meeting was held under the chairpersonship of Shri B Bhamathi AS (CS) MHA at North Block, MHA, New Delhi. The following points concerning CCTNS were discussed:
|
| 174. | 17-07-12 |
Process Advisory Group (PAG)
meeting was held under the Chairpersonship of Smt. B. Bhamathi,
Additional Secretary (CS)at North Block, MHA New Delhi. |
| 175. | 06-08-12 |
User
Acceptance Testing (UAT round 4) of Core Application Software for CCTNS
project had started at NCRB Office, R.K. Puram New Delhi from 6th August
2012 to 22nd August 2012. The participating states were Chandigarh,
Haryana, Himachal Pradesh, Madhya Pradesh and Bihar. UAT round 4 was
completed |
| 176. | 30-08-12 |
System
Integrator’s one day workshop for CCTNS project was held under the
Chairmanship of Shri P. R. K Naidu, Joint Director (CCTNS) at the
Conference Hall, NCRB, New Delhi. The participating States/UTs were
those states where SIs have been selected or shortlisted. The States/UTs
were Andaman & Nicobar Islands, Andhra Pradesh, Assam, Bihar,
Chhattisgarh, Dadar& Nagar Haveli, Delhi, Goa, Haryana, Himachal
Pradesh, Jammu & Kashmir, Jharkhand, Karnataka, Kerala, Madhya Pradesh,
Meghalaya, Mizoram, Nagaland, Odisha, Rajasthan, Sikkim, Tripura, Uttar
Pradesh and West Bengal. |
| 177. | 21-09-12 |
SDA Steering committee meeting was held under the Chairpersonship of Smt. B. Bhamathi, Additional Secretary (CS) at the North Block, MHA New Delhi. |
| 178. | 09-10-2012 |
User Acceptance Testing (UAT round 5) of Core Application Software for CCTNS project had started at NCRB Office, R.K. Puram New Delhi from 9th October 2012 to 19th October 2012. |
| 179. | 29-10-2012 |
User Acceptance Testing (UAT round 6) of Core Application Software for CCTNS project had started at NCRB Office, R.K. Puram New Delhi from 29th October 2012 to 9th November 2012. |
| 180. |
29-10-2012 & 30-10-2012 |
Walkthrough Session of Core Application Software was held Under the Chairmanship of Shri Shafi Alam, Director General (NCRB) at the Conference Hall, NCRB, New Delhi. |
| 181. | 07-11-2012 |
Union Home Secretary review meeting w.r.t CCTNS was held with CCTNS nodal Officers under the Chairmanship of Home Secretary at North Block, MHA New Delhi. |
| 182. | 21-11-2012 |
A meeting for Integration of various applications like eCourts, ePrisons of Criminal Justice system with CCTNS was held under the chairmanship of Sh. P. R. K Naidu at NCRB Office, East Block- 7, R. K Puram, New Delhi. |
| 183. | 21-11-2012 |
A regional workshop for Pilot Go-live for North Eastern states was held under the chairmanship of Sh. P. R. K Naidu, Joint Director of NCRB (CCTNS) at Police Headquarters, Ulubari, Guwahati, Assam. |
| 184. |
05-12-2012 & 06-12-2012 |
CCTNS review meeting with all the System Integrators of States/Uts was held under the chairmanship of Sh. S. Suresh Kumar, JS (CS) at Conference room, MHA, NDCC-II, New Delhi. |
| 185. | 06-12-2012 |
A full day workshop regarding the deployment and
configuration of CAS application at States/UTs was conducted under the
chairpersonship of Shm. B. Radhika, Joint Director of NCRB at NCRB
office, east Block- 7, R. K. Puram New Delhi.
|
| 186. | 07-12-2013 |
A second meeting regarding Integration of various applications like eCourts, ePrisons of Criminal Justice System with CCTNS was held under the chairmanship of Sh. P. R. K Naidu, Joint Director of NCRB (CCTNS) at NCRB office, East Block-7, R. K. Puram, New Delhi. |
| 187. | 20-12-2012 |
A meeting for Integration of various applications like eCourts, ePrisons of Criminal Justice system with CCTNS was held under the chairmanship of Sh. K. Skandan, AS (CS) at North Block, MHA. New Delhi. |
| 188. | 04-01-2013 |
The Pilot phase of CCTNS was launched by Hon’ble Home minister Sh. Sushil Kumar Shinde at Vigyan Bhawan, New Delhi. |
| 189. | 07-01-2013 |
Review meeting of NCRB w.r.t administrative matters and CCTNS matters and CCTNS project was held under the chairmanship of Sh. R. K Singh, Home Secretary at North Block, MHA, New Delhi. DG, NCRB welcomed Home Secretary and briefly enlightened about the organization and mandate of NCRB which include Crime Statistics, Training, Management of Finger print database and Crime Criminal Tracking network and system project (CCTNS). |
| 190. | 16-01-2013 |
Central e-Mission Team (CeMT) meeting was held under the chairmanship of Sh. S. Suresh Kumar, JS (CS) to discuss the status of CAS application and 3 Pilot States’ sites network Connectivity at MHA, New Delhi. |
| 191. | 30-01-2013 |
A meeting was conducted with eCommittee team, Supreme Court of India for integration of eCourts and ePrisons applications with CCTNS at Supreme Court Guest House, New Delhi |
| 192. | 31-01-2013 |
CCTNS project progress review meeting was held under the chairmanship of Sh. S. Suresh Kumar, JS (CS) with all the CCTNS State/UTs project management Units across all the States/UTs at Media room North Block, MHA, and New Delhi. |
| 193. | 31-01-2013 |
A National Level Workshop was organised for pilot launch
of Citizen services of CCTNS project under the Chairmanship of Shri P.
R. K Naidu, Joint Director of NCRB (CCTNS) at the CRPF Officers
Institute, Shaurya, New Delhi. |
| 194. | 01-02-2013 |
Nodal Officers’ Review meeting was held under the
chairmanship of Sh. S. Suresh Kumar, JS (CS) to discuss overall CCTNS
project progress status at North Block, MHA, New Delhi.
|
| 195. | 14-02-2013 |
A Walk-through of Core Application Software (CAS) to Shri R. Sreekumar, Chief Vigilance Commissioner was conducted at Conference Hall, NCRB Office , R. K. Puram New Delhi. |
| 196. | 15-02-2013 |
A meeting was held under the Chairmanship of Sh. Shafi Alam, DG, NCRB to discuss and signing of SI contract in Arunachal Pradesh by M/s Rolta Limited at NCRB Office, Block- 7, R.K.Puram, New Delhi. |
| 197. |
19-02-2013 & 20-02-2013 |
A National level workshop on Change Management w.r.t CCTNS project was organised by NCRB at NDCC Convention Centre, NDCC, MHA New Delhi. |
| 198. | 11-03-2013 |
CCTNS Project review meeting was held under the chairmanship of Sh. K. Skandan, AS (CS) at North Block MHA, New Delhi. |
| 199. | 14-03-2013 |
A meeting with Sh. J. Satyanarayana, Secretary of Diety, Ministry of communications and Information Technology, to discuss the various issues concerning CCTNS project at Diety office, New Delhi. |
| 200. | 15-03-2013 |
CAS review meeting was held under the Chairmanship of Sh. Shafi Alam, DG of NCRB to discuss the delay and quality related issues pertaining to CAS and related documentation at NCRB office, Block- 7, R. K. Puram, New Delhi. |
| 201. | 18-03-2013 |
A video conferencing meeting was conducted from 18th March 2013 to 3rd April 2013 to review and discuss the progress of CCTNS Project implementation across all States/Uts at NCRB Office, Block- 7, R. K. Puram, New Delhi. |